Commercial intelligence for erection engineering & heavy lifting — the decisions, sequences, and risks behind the world's most complex lifts.
Oct 26, 2026
•
4 min read
The bid assumed bolted arch boxes of up to 400 tonnes. A design review moved the joints to site welds.
Oct 19, 2026
3 min read
A proof-test interrupted the lift. The ceremony date held. The public opening came later.
Oct 11, 2026
8 min read
Three teams priced a new Hudson River crossing in 2012. The lowest came in $848 million below the next, with less dredging, fewer piles and a shorter proposed programme. Behind it sat a design and an erection method developed together.
Oct 5, 2026
6 min read
One jack-up. One drill. Four installation sequences, selected position by position, with a borehole at every monopile location to establish the base of the calcarenite and the end of drilling.
Sep 28, 2026
A crane vessel's lifting capability helped set the diameter of one of the world's deepest floating production platforms.
Sep 21, 2026
Chenab Bridge, India: the world's highest railway bridge — and a case study in what a contract owes a contractor when the erection method can't be spread across a fleet, only recovered on the one project it was built for.